Jeff Davis Parish jail delayed by construction again
<p class="p1">JENNINGS — Jeff Davis Parish’s new $9.4 million regional jail was to open earlier this month, but construction delays continue to put the project behind.
<p class="p1">“They are still doing a lot of work and are not finished,” Police Jury President Donald Woods said Wednesday.
<p class="p1">“I have not been out there to find out how much they are behind. Our contractor and engineer were out there today, but have not reported back yet.”
<p class="p1">The jail was to be completed in early 2018, but unforeseen circumstances — weather issues, delayed equipment delivery, relocation of a fence, and driers that won’t fit through the doors — have hindered completion.
<p class="p1">Police jurors this week approved a ninth change order for the jail, in the amount of $3,482, for installing electrical wiring for the gate. The wiring wasn’t put in the original contract, Woods said.
<p class="p1">Police Jury attorney David Bruchhaus said the panel won’t accept the project as substantially complete for occupancy until everything is completed to satisfaction per the contract.
{{tncms-inline content="&lt;p class=&quot;p1&quot;&gt;&lt;strong&gt;&amp;lsquo;They are still doing a lot of work and are not finished.&amp;rsquo;&lt;/strong&gt;&lt;/p&gt; &lt;p class=&quot;p3&quot;&gt;&lt;strong&gt;Donald Woods&lt;/strong&gt;&lt;/p&gt; &lt;p class=&quot;p4&quot;&gt;Jeff Davis Police Jury president&lt;/p&gt;" id="5e928803-e838-4069-a7e6-9fc60ee0f2a2" style-type="quote" title="Pull Quote" type="relcontent"}}
<p class="p1">The parish may have the option to withhold a retainage fee until the project is certified as substantially complete by the architect and engineer.
<p class="p1">Construction on the 31,000-square-foot facility began shortly after groundbreaking in July 2016.
<p class="p1">The new jail, on a 17.5-acre site off U.S. 90 just west of Jennings, will have 200 beds, a central control room, separate recreation yards for male and female inmates, isolation cells and a vehicular sally port.
<p class="p1">Plans for the facility are based on a 2012 feasibility study that called for the replacement of the current 65-bed parish jail, which officials said is undersized, outdated and in need of costly repairs.
<p class="p1"><strong>‘They are still doing a lot of work and are not finished.’</strong>
<p class="p3"><strong>Donald Woods</strong>
<p class="p4">Jeff Davis Police Jury president